As of December 31st 2013 the Gate Project is 99.6% complete. The breakdown is as follows:

Area

% complete

Area

% complete

The Gate Tower 1

100%

The Arc Tower

99.46%

The Gate Tower 2

100%

Podium

99.1%

The Gate Tower 3

99.79%

Landscaping

100%

Penthouse Bridge

93%

   

The contractor’s main ongoing activities are:

1) De-Snagging works for all towers

2) Snagging works for Penthouse Bridge

Tower 1 TOC was granted on 29 Sep 13, Tower 2 TOC was granted on 31st October 2013& Tower 3 TOC will be issued in Decmber 2013. Completion and handing over of balance works are expected by February 2014